Street Projects

The City of Richmond Heights works hard to keep it's infrastructure safe. See the list below of street projects in the City.

Check back regularly to see what's happening around town.

Street Projects

Dale Avenue Water Main Replacement Project
  • The water main on Dale Avenue will be replaced between Hanley Road and Big Bend
    • JH Berra has been awarded project and will start January 10th
    • Residents have been sent letters along Dale and received robocalls from MOAW
    • JH Berra replaced water main on Dale (east of Big Bend) and Big Bend in 2019 and has performed good work in the past within Richmond Heights
    • JH Berra will be starting the week of January 10th at the Hampton Branch Creek crossing and move towards Hanley Road in the east bound lane.
    • Soon after crews will begin heading east from Hampton Branch Creek in the eastbound lane.
  • Per contract, all water main shall be in the ground by end of April and all service transfers and pavement restoration shall be completed by end of July, weather dependent. 
Lovella Avenue Bridge Replacement Project
The City of Richmond Heights secured a federal grant to replace the bridge culvert on Lovella Avenue over Claytonia Creek.  MSD teamed up with us and added a small storm sewer separation project between Moorlands and Claytonia Creek also.

The schedule for the project is as follow:

Design - 2019
Right of Way and temporary easement acquisitions (if needed) - 2020
Construction - 2021/2022

Overall Project Boundary Map
This map identifies the overall project boundary of where these services will be performed.

April 11, 2022
The Bridge construction is complete.  The roadway is open to the public.

July 23, 2021
The bridge deck has been removed and work will begin on the new structure.

June 21, 2021
Storm sewer work is expected to start tomorrow (June 22) and the road will be closed at the bridge. Traffic control will be up this afternoon. If all goes well, the storm sewer work will take ~10 days to complete, but the bridge will be closed until the project is complete as the bridge demo will be after the storm sewer work.
 
June 3, 2021 Update:
Raineri anticipates starting the project the week of June 21.  They will start mobilizing and prepping the site the week before and the start installing storm sewers along Moorlands and Lovella.  Once the bridge demolition begins, the bridge and the area of the project will be closed to through traffic until the work is completed.  THe contractor has 120 days to complete the project.

April 14, 2021 Update:
We are currently in the process of approving the contract for Raineri Construction to construct the project.  The anticipated start date is mid-May.  The project will take 3-4 months to complete once construction begins.

January 23, 2019 Update:
All survey and design contracts with MODOT and MSD have been approved.  Oates Associates will begin survey late January or early February depending on weather.  You will start to see colored flags and paint in the street and yard areas as utilities will be located for the surveyor to pickup for design.
Del Norte and La Veta Avenue - Missouri American Water Main Replacement Project
April 2022 Update:
MOAW has hired ECM Construction to replace the watermain and services on Del Norte and La Veta Avenue.  The watermain on Del Norte will be replaced between Bruno Avenue and La Veta Avenue and the watermain on La Veta will be replaced between Bellevue Avenue and Del Norte Avenue.  

Construction is scheduled to start the first week in June after schools are out for the summer.  The watermain should be installed in the ground within 8 weeks with service work to immediately follow.  

ECM will be responsible for all roadway restoration work on La Veta.  ECM will only be installing a temporary asphalt patch on Del Norte as the City has a planned project starting in the spring of 2023 to reconstruct the street, sidewalk and driveway approaches.

ECM is scheduled to complete their portion of the project, including road restorations by the end of November.