• The water main on Dale Avenue will be replaced between Hanley Road and Big Bend
    • JH Berra has been awarded project and will start January 10th
    • Residents have been sent letters along Dale and received robocalls from MOAW
    • JH Berra replaced water main on Dale (east of Big Bend) and Big Bend in 2019 and has performed good work in the past within Richmond Heights
    • JH Berra will be starting the week of January 10th at the Hampton Branch Creek crossing and move towards Hanley Road in the east bound lane.
    • Soon after crews will begin heading east from Hampton Branch Creek in the eastbound lane.
  • Per contract, all water main shall be in the ground by end of April and all service transfers and pavement restoration shall be completed by end of July, weather dependent.