Claytonia Terrace Road Work

Sweetens Concrete started sawcutting on Tuesday, April 21, 2020 and removed the blue section (see image below) on Wednesday, April 22.

Letters were given to affected homeowners with further instructions.  

May 6, 2020 - Northbound work (Red/Purple/Orange colors) is expected to begin soon and last for the next few weeks. 

June 10, 2020 - Last section is being removed today and further restoration work on driveways, etc will continue. Project is expected to be finished by the end of June, weather permitting.

Claytonia Terrace 2020 Project